June 2018 
After years of searching for a larger facility to accommodate the waiting list for our many programs and events we found our dream location.
 
With the help and guidance of our dear friends and pillars of the community, Mr. Sandy Feld and Mr. Evan Makovsky and the team at Shames-Makovsky we went into escrow for the beautiful former Beacon Country Day School.  A magnificent five acre campus centrally located just west of I-25 on Belleview Avenue.
With close to 23,000 square feet of indoor space including classrooms, a gymnasium, offices and the potential for so much more.
 
August 2018
A team of volunteers made up of community leaders from throughout all segments of the community joined together to plan how we can turn this amazing dream into a reality.
 
Due Diligence
Over the next couple of months we hired professionals to inspect the building including environmental survey, roof, plumbing, foundation and structure, sewer wiring, checking for asbestos, lead and so much more.
 
Architect
John Garner of John Gardner Architect was brought on board to design the interior and work with the City of Greenwood Village Planning and Zoning Commission and City Council to get the plans approved.
 
John has over 30 years of experience  in designing schools, community centers, and many building uses throughout metro Denver and beyond.
 
Security Team
we are blessed and fortunate to have an amazing and dedicated security team of volunteers.
 
From the beginning of the process Ben, Alden, David and Harry walked us through every step of the way to make sure that the entire campus is safe and secure.
 
Interior Design
Erica Gardner of Gardner Gray Interior was brought on board to help with interior design. Erica, who is a dear friend of Chabad, has many years of experience bringing warmth, light and comfort to every space she works with, giving a welcoming and beautiful touch.
 
Construction company and Owner’s Representative 
Barry Gilbert of Gilbert Construction has many years experience building some of the  areas most beautiful and well-known buildings throughout the state, including five star hotels, office towers, schools and much more.
We are thrilled that Barry, Andy and their team took on our project.
 
Zoning
We reached out to all neighbors inviting them to a neighborhood input meeting at Greenwood Village City Hall.
Our goal is to be a good neighbor and see how we can take everyone's interest in mind as the project moves forward.
Many neighbors shared their excitement about the project.
 
 
Chanukah Menorah Lighting Celebration at Greenwood Village City Hall
Rabbi Mintz welcomed the hundreds of people to the annual menorah lighting celebration at Greenwood Village City Hall.
Honored with lighting the menorah was Greenwood Village Mayor, along with council members and the former mayor, as well as Congressman Mike Coffman.
 
Planning and Zoning Committee.
At the first meeting Sandy Feld Rabbi and Hindy Mintz and John Garner addressed the planning and zoning committee.
 
City Council Meeting
All members of the Greenwood Village City Council unanimously approved the zoning and use of 6100 E. Belleview Ave. They included their best wishes and welcomed us to Greenwood Village.
 
Financing through First Bank.
Mr Jonathan Hambourger led the effort to acquire financing, and in creating a financial plan to move forward with this exciting project.
 
MAZEL TOV - WE CLOSED!
Closed on Property September 3, 2019.
 
September 3, 2019
Construction plans were complete and ready to go once we closed on the property. Sure enough, that same day demolition was started with the gutting of the building.
 
Plumbing & Electrical

Heating and air conditioning
 
Framing & Drywall
 
Flooring
 
Elevator
 
Fire Alarm and Fire Sprinkler
 
Painting
 
Special covid-19 Modifications

We are excited to share that we purchased special air systems that allow for MERV 13 Filters to be installed, ensuring and provided the most cleanest possible air circulation and ventilation.
Additionally, the large indoor and outdoor space allows for more flexibility for the children.  
 
August 12, 2020
Final Inspection and Certificate of Occupancy
 
August 17, 2020
Phase One Complete
 
August 24, 2020
First day of Garden Preschool & Early Learning Center at the new facility